MPSC case U-16306
In the matter of the application of EDISON SAULT ELECTRIC COMPANY for authority to reconcile its energy optimization plan costs associated with the plan approved in Case No. U-15807, for the period ended December 31, 2009.
MPSC case U-16306 is an electric-industry case before the Michigan Public Service Commission that the commission's case index lists as opened March 31, 2010.
Summary
- Industry
- Electric
- Opened
- March 31, 2010 (as the publisher's index lists it)
- MPSC case number
- U-16306
Stored facts1
Related records1
Source publishers1
Case status
Follow the record
Read the dated facts and the documents behind them.
Timeline
- The Michigan Public Service Commission decided the case. The outcome it states is "approved a settlement agreement."
Sources
- Michigan Public Service Commission: order, Aug. 30, 2010