MPSC case U-17912
In the matter of the application of WISCONSIN ELECTRIC POWER COMPANY d/b/a We Energies for approval of a power supply cost recovery plan and authorization of monthly power supply cost recovery factors for the calendar year 2016.
MPSC case U-17912 is an electric-industry case before the Michigan Public Service Commission that the commission's case index lists as opened Oct. 1, 2015.
Summary
- Industry
- Electric
- Opened
- Oct. 1, 2015 (as the publisher's index lists it)
- MPSC case number
- U-17912
Stored facts1
Related records1
Source publishers1
Case status
Follow the record
Read the dated facts and the documents behind them.
Timeline
- The Michigan Public Service Commission decided the case. The outcome it states is "approved a settlement agreement."
Sources
- Michigan Public Service Commission: order, March 29, 2016