The Michigan Court of Appeals issued a published opinion Nov. 23, 2026; the opinion says it affirms an order affirming the issuance of tall structure permits to Pegasus Wind, LLC.
The opinion says Tuscola Area Airport Authority appealed the Ingham Circuit Court order affirming the Michigan Department of Transportation’s issuance of the permits. The opinion says the department never issued a written finding expressly stating that Pegasus’s proposed project would not interfere with air navigation.
The opinion says the airport authority argued that the department “never independently determined that Pegasus’s project would not interfere with air navigation.” The opinion says the Tall Structure Act requires the department to find that a proposed project would not interfere with air navigation before issuing tall structure permits.
The opinion says the parties disputed whether the department’s review of application materials, including the Capitol Airspace study, met the requirement to conduct an airspace study. The opinion says the act does not define an airspace study or specify what form a noninterference finding must take.
The opinion says the Legislature’s intent to require writing in one portion of the act, but not another, suggests it did not intend to require a written airspace study. The opinion says the act neither defined how the department must make a noninterference finding “nor stated that such a finding must be in writing.”
The Court of Appeals granted a motion to reschedule oral argument in docket 373184 on Aug. 4, 2026. The Michigan Supreme Court and Court of Appeals opinions and orders list nothing on the docket dated after Nov. 23, 2026, as of Nov. 25, 2026.
The opinion says the statute does not require the department to conduct a certain kind of study or issue a certain report.