Gov. Gretchen Whitmer said Nov. 24, 2026, that the Michigan Department of Environment, Great Lakes, and Energy had been directed to suspend further action on its Line 5 Tunnel Project permits.
Map sources
Pipeline: U.S. Energy Information Administration, crude oil trunk pipelines as of January 2020, generalized for maps no larger than 1:1,000,000, retrieved Nov. 25, 2026. Lakes and neighbouring land: Census Bureau 2023 cartographic boundaries (1:5,000,000); Natural Earth 1:10m admin 0 countries; USGS 3D Hydrography Program. The EIA layer names the line Lakehead; its route matches the Line 5 route described in the Michigan Public Service Commission's order of Dec. 1, 2023, in case U-20763. Boundaries: Michigan Geographic Framework, DTMB Center for Shared Solutions, retrieved Sept. 24, 2026. Water: USGS 3D Hydrography Program, retrieved Sept. 26, 2026. Roads: Census Bureau TIGER/Line 2025. Locator: Census Bureau 2023 cartographic boundaries; Natural Earth 5.1.1.
Whitmer said, “I have always said my ultimate goal is to get Line 5 out of the water.” On Sept. 9, Whitmer said the existing dual Line 5 pipelines in the Straits of Mackinac were 73 years old.
Map sources
Pipelines and cables: NOAA Office of Coast Survey, Electronic Navigational Charts, cells US4MI1ND (edition 1, update 5, issued Dec. 17, 2025); US4MI2NS (edition 3, update 0, issued Sept. 17, 2025), retrieved Nov. 25, 2026. Place names: U.S. Geological Survey, Geographic Names Information System, retrieved Sept. 26, 2026. The chart does not name the pipelines' owner; the Michigan Public Service Commission's order of Dec. 1, 2023, in case U-20763 describes Line 5's Straits segment as two 20-inch pipes, four miles long, and these are the only charted pipelines that cross the Straits. Boundaries: Michigan Geographic Framework, DTMB Center for Shared Solutions, retrieved Sept. 24, 2026. Water: USGS 3D Hydrography Program, retrieved Sept. 26, 2026. Roads: Census Bureau TIGER/Line 2025. Locator: Census Bureau 2023 cartographic boundaries; Natural Earth 5.1.1.
Attorney General Dana Nessel said April 22, 2026, that a unanimous U.S. Supreme Court ruling “makes emphatically clear that our lawsuit against Enbridge belongs before the state court.”
The Michigan Supreme Court reversed the Court of Appeals judgment, vacated a commission order, and sent the case back to the commission for further proceedings on July 31, 2026, in docket 168335.
The governor sent a letter to Enbridge’s CEO on Sept. 9, 2026; the governor’s press release said it called on the company to “stop treating the tunnel as the only alternative to the existing dual pipelines.”
The Michigan Supreme Court denied a motion for rehearing in the case on Sept. 23, 2026.
- The Michigan Supreme Court reversed the Court of Appeals judgment, vacated a commission order, and sent the case back to the commission for further proceedings in docket 168335.
- Gov. Gretchen Whitmer sent a letter to Enbridge’s CEO; the governor’s press release said it called on the company to “stop treating the tunnel as the only alternative to the existing dual pipelines.”
- The Michigan Supreme Court denied a motion for rehearing in the case.
- Gov. Gretchen Whitmer said that the Michigan Department of Environment, Great Lakes, and Energy had been directed to suspend further action on its Line 5 Tunnel Project permits.
Source: Michigan Supreme Court; Michigan Court of Appeals; Office of the Governor.