Enbridge will again seek a permit from the state utility commission for its Line 5 tunnel, and the state environmental department is to suspend work on tunnel permits, Gov. Gretchen Whitmer's Nov. 24 release says.

The release says the Michigan Department of Environment, Great Lakes, and Energy (EGLE) is to "suspend further action on the resource and pending wastewater permits" for the tunnel until legal questions are resolved. EGLE announced its decision on the resource permit July 15.

Whitmer said, "Given what is at stake, and the Michigan Supreme Court’s recent decision, I have directed EGLE to suspend further action on its Line 5 Tunnel Project permits at this time." The release says the state also has a position before a federal court of appeals following a December 2025 ruling.

The Michigan Supreme Court on July 31, 2026, vacated the Michigan Public Service Commission's Dec. 1, 2023, order approving Enbridge's application and sent the case back to the commission. Michigan Advance reported that the court found the commission had not properly considered environmental harms that could arise from extending the pipeline's lifespan. The court denied rehearing Sept. 23, 2026.

The commission's E-Dockets order documents list nothing in the case, U-20763, dated after Dec. 1, 2023, as of Nov. 28, 2026. The tunnel project requires several other permits, including from the Department of Natural Resources, the commission and the U.S. Army Corps of Engineers, EGLE said. Michigan Advance reported that pipeline opponents filed two requests for a contested case on the permits EGLE approved in July.

Line 5 runs 645 miles from northwest Wisconsin to southwest Ontario and includes a 4.5-mile dual segment on the bed of the Straits of Mackinac, Michigan Advance reported. The commission approved the line's construction in 1953 for Enbridge's predecessor, and the Michigan Conservation Commission granted an easement for two 20-inch pipes across the straits, the court's opinion says.

Enbridge applied to the commission to build a tunnel under the straits to house a portion of Line 5, the opinion says. The commission set the application for a hearing June 30, 2020, and reopened the record for more testimony and exhibits July 7, 2022.

While an appeal was pending, Whitmer issued a notice revoking the 1953 easement, and the commission sent the case back to an administrative law judge to consider the effect, the opinion says.

The commission's Dec. 1, 2023, order authorized the project on the condition that Enbridge secure the necessary government permits, and the Court of Appeals affirmed it in a published decision, the opinion says. The Supreme Court agreed to hear the appeal Sept. 19, 2025.

"I have always said my ultimate goal is to get Line 5 out of the water," Whitmer said Nov. 24. Enbridge spokesperson Ryan Duffy said the court's decision had introduced new uncertainty "even as the permitting record remains strong," Michigan Advance reported.

Sequence of events
  1. The Michigan Public Service Commission set the application for a hearing June 30, 2020, and reopened the record for more testimony and exhibits July 7, 2022.
  2. The Supreme Court agreed to hear the appeal Sept. 19, 2025.
  3. The Michigan Supreme Court, vacated the Michigan Public Service Commission's Dec. 1, 2023, order approving Enbridge's application and sent the case back to the commission.
  4. The Michigan Supreme Court denied rehearing Sept. 23, 2026.
  5. Enbridge will again seek a permit from the state utility commission for its Line 5 tunnel, and the state environmental department is to suspend work on tunnel permits, Gov. Gretchen Whitmer's Nov. 24 release says.

Source: openmpsc.com; Michigan Supreme Court; Michigan Court of Appeals; Office of the Governor.